Fire protection coordination is the process of fitting fire protection systems into a building without clashing with the structure or the MEP systems (mechanical, electrical and plumbing). These systems include sprinklers, risers, alarms and smoke control equipment. When structural and MEP teams work in separate models, conflicts can appear late.
In this article, gbc engineers explains 7 fire protection coordination challenges between structural and MEP systems and how developers can reduce the risk. Each section explains why the problem happens and what to agree early.
Why fire protection coordination can happen last
Fire protection can be coordinated last because the structure and the main MEP systems are designed first. The sprinkler layout can follow later and is sometimes drawn by a specialist contractor. By then beam depths, shafts and ceiling heights are fixed.
1. Sprinkler mains and ducts compete for the same ceiling space
Sprinkler mains and large air ducts compete for the same space above the ceiling. Ducts are bulky and sprinkler pipes need hangers, valves and access.
Without a shared model the contractor moves one of them on site. Ceiling height may be what is lost. For developers this can mean less clear height under beams and less room for future services. Agreeing on service zones (the ceiling space reserved for each system) early in fire protection coordination can prevent most of these conflicts.
2. Pipe openings in beams and slabs need structural approval
Sprinkler pipes pass through openings in beams and slabs. The structural engineer must approve each opening. A badly placed opening can cut the steel reinforcement inside the concrete.
Post-tensioned slabs are strengthened by tensioned steel cables. An opening that hits one of these cables is a serious safety risk. Openings in fire-rated floors also need space for firestopping.
The best approach to fire protection coordination is to show every opening on the structural drawings before the concrete is poured. Drilling later can mean scanning the slab first and getting engineering approval.
Read more: The Structural Design Decisions Behind Every Fire-Safe Building
3. Risers clash with structural walls and bracing in shafts
Risers clash with structural walls and bracing because both need space in shafts and stair cores. Risers are the vertical pipes that carry water up the building.
A pipe can be shifted by a few inches. A braced frame or shear wall cannot easily move once the structural design is set. Fixing the shaft layout early in fire protection coordination avoids late changes to structural connections.
4. Beam depth limits where sprinkler heads can go
Beam depth can limit where sprinkler heads can go. Beams, light fixtures and ducts can all obstruct sprinkler discharge. NFPA 13 (2025 edition) is a widely used standard for sprinkler installation and includes requirements for positioning sprinklers relative to obstructions.
Depending on the ceiling configuration and sprinkler type, a deeper beam may require additional sprinkler heads or a different layout. In Europe, sprinkler systems may be designed in accordance with standards such as EN 12845:2015+A2:2026 (published as DIN EN 12845:2026-09 in Germany) or guidelines such as VdS CEA 4001 (2024 edition), depending on the applicable project requirements.
The architect, structural engineer and fire protection designer should check beam depth against the ceiling plan together as part of fire protection coordination.

5. Pipes crossing seismic and expansion joints must allow for movement
Sprinkler pipes need flexible connections where they cross seismic joints, because rigid pipe cannot follow a moving building. A seismic joint is a deliberate gap that lets 2 parts of a building move separately in an earthquake.
In buildings that need seismic design, NFPA 13 calls for a seismic separation assembly where sprinkler pipe crosses a building seismic joint. The assembly uses flexible fittings or flexible piping so the pipe can follow the movement. Expansion joints raise a similar issue.
If joint positions are confirmed late, the space for these assemblies can be missing. In fire protection coordination, the team should confirm which joints exist and how far each one can move before pipe routes are drawn.
Read more: How Climate Change Is Changing Structural Design
6. Late reroutes can reduce water pressure at the sprinkler heads
Late reroutes can reduce sprinkler pressure because pipe sizes are calculated for a specific route. Every extra bend or longer run adds friction. That lowers the water pressure at the sprinkler heads.
In fire protection coordination, a reroute around a beam or cable tray requires updated hydraulic calculations and sometimes a larger pipe. For developers the risk is a sprinkler system that looks complete on site but no longer delivers the water the design assumed.
7. Alarms, smoke control and HVAC must work as one sequence
Fire alarms, smoke control and HVAC (heating, ventilation and air conditioning) have to work as one sequence. In many buildings the HVAC fans and dampers (airflow controls inside ducts) change their operating mode to control smoke when the system is activated.
This sequence involves fire protection, mechanical and electrical contractors. Gaps between their scopes can appear in fire protection coordination. Testing checks each component first and then the whole sequence.
For developers this is a handover risk. Smoke control commissioning (final testing before handover) is a lengthy process that needs planning from the start of the project to avoid delaying deadlines. Smoke control fans and shafts can also add loads and openings that the structure must allow for.
How gbc engineers supports structural and MEP coordination for fire protection
gbc engineers provides structural engineering and Building Information Modeling (BIM) services. These include clash detection and BIM coordination in a shared environment for all stakeholders. In a shared model the fire protection and MEP designers can see beam depths, shafts, joints and openings before pipe routes are fixed. Fire protection design itself stays with the specialist designer.
Precast expertise adds another reason to coordinate early. Precast elements are made in a factory, so openings can be cast in and must be settled before production starts. A late change needs engineering review and may require a new element.
Read more: 6 BIM Trends Shaping Construction | gbc engineers
Conclusion
Most of these challenges start with the same gap, because structural and MEP information can reach the fire protection designer too late. Developers can close it with 3 requests. They are a coordinated model before fire protection shop drawings start, fixed shaft and joint positions and a rule that every site change to pipe routes goes back to the designers.
Frequently asked questions
What is MEP coordination?
MEP coordination is the process of resolving clashes between mechanical, electrical and plumbing systems and the structure before construction starts. Fire protection can be coordinated alongside it.
What does BIM clash detection check in fire protection coordination?
BIM clash detection compares the 3D models of each discipline and flags where 2 elements occupy the same space, such as a pipe passing through a beam. It checks geometry only, so code rules such as sprinkler obstruction distances still need review by the designer.
What is firestopping in fire protection coordination?
Firestopping is the sealing of gaps around pipes and cables that pass through fire-rated floors and walls. It stops fire and smoke from spreading through the opening. The opening must be sized to leave room for it.
Who is responsible for fire protection coordination?
Responsibility is shared and the contract sets who leads. The fire protection designer owns the sprinkler design. The structural engineer approves openings. The BIM coordinator can run the clash checks.
When should fire protection be coordinated with structural design?
At concept stage, before beam depths, shafts and joint positions are fixed. After that every conflict becomes a site change.
|
About us
gbc engineers
is an international engineering consultancy with offices in Germany, Poland, and South East Asia, having delivered 500+ projects worldwide. We provide services in structural engineering, data center design, infrastructure and bridge engineering, BIM & Scan-to-BIM, and construction management. Combining German engineering quality with international expertise, we achieve sustainable, safe, and efficient solutions for our clients.
|